If a project or a project task is marked Closed, the project manager can complete the
associated Allocated resource plans. Similarly, the demand manager can complete the resource
plans for a Closed or Deferred demand.
When a project or a project task moves to Closed Complete, Closed Incomplete or
Closed Skipped state, the system prompts a message on the project and project task
forms, and in the planning console for completing the Allocated resource plans
if
- there is a corresponding resource plan in the Allocated state. And,
- the resource plan start date is less than or equal to the project or task actual
end date.
A similar message for completing the resource plans appears on the Demand form when a
demand moves to Closed or Deferred state.