Associate a time card with a resource plan

If one resource is allocated to identically named tasks in two resource plans, use the following procedure to specify the resource plan the time card should be allocated to.

  1. Navigate to the Time Cards > All.
  2. Select a time card.
  3. Configure the form to add the Resource plan field.
  4. In Resource plan, select the plan to allocate the time card to. Only resource plans that contain the task are listed.
    Figure 1. Time Card with Resource Plan
  5. Click Update.