Update the details of the dependency including its type and lag time from Project Workspace.

Before you begin

Role required: it_project_manager

Procedure

  1. Open a project from the planning page of Project Workspace.
    For information on how to navigate to the planning page, see Access the new Project Workspace.
  2. Open the dependency side panel in one of the two ways.
    OptionAction
    From the data grid From the dependency column, click the dependency of the task.
    From the timeline view Click the dependency line.
  3. Edit the fields.
  4. Select Update.