Generate workflow activity
-
- UpdatedAug 3, 2023
- 3 minutes to read
- Vancouver
- Workflow
The Generate activity immediately creates task or approval records from any task or approval activities placed after the Generate activity in the workflow path. These pre-generated tasks and approvals start when the task and approval activities are reached during flow execution. This allows a task to have a set of associated pre-generated sequential tasks or approvals, but still require them to be completed in order.
By default, the workflow does not create any tasks or approvals until it reaches them in the workflow.
- If it is a task activity,
creates the task and sets:
- The State to Pending
- The Expected Start Date
- The Due Date
Note: Task activities run as the user whose actions complete the task the workflow was waiting for and advances the workflow. - If it is an approval activity, creates the approvals and sets:
- The approval State to Not Requested
- The Expected Start Date
- The Due Date
Note: Approval activities run as the user whose actions match the approve or reject conditions the workflow was waiting for and advances the workflow.
Expected start dates and due dates are calculated based on the Expected Duration of all of the tasks and approvals between the Generate activity and the activity being updated. In the case of a branched path (between a Branch and Join activity), the longer duration will be used for any post-branch activities.
The Generate activity can be used more than once, and any tasks or approvals will be refreshed with updated information. This is useful in situations where the list of approvers or other important information is still editable while the workflow is in process and it may be necessary to update or correct the generated approvals or tasks.
- Rejected (for any of the approval activities)
- No condition of If activity
- Continue condition of Turnstile activity
- Incomplete condition of Join activity
Input variables
Input variables determine the initial behavior of the activity.
Field | Description |
---|---|
Generate approvals | If selected, approvals are created when running the Generate activity. If cleared, the approvals are used to compute their estimated duration, but no approvals are created. |
Generate tasks | If selected, tasks are created when running the Generate activity. If cleared, the tasks are used to compute their estimated duration, but no tasks are created. |
States
State | Description |
---|---|
Executing | The activity is executing. |
Finished | The activity finished running. See the result value for the outcome of the activity. |
Cancelled | This activity, or the workflow that contains this activity, was canceled. |
Example

- Approval-2
- Approval-3
Approval-4 is skipped since the Rejected condition of Approval-3 has Skip during generate selected.

Notice that Task 5 starts on Jan. 4, 2016 since the longest path (based on due dates) to the Join is Task 3/Task 4.