Change default values of copied project
-
- UpdatedJan 30, 2025
- 2 minutes to read
- Yokohama
- Project Portfolio Management
Reset or change the default values for copied fields in the new copied partial or complete project.
Before you begin
Role required: admin
About this task
Child tasks are defined with the same relationships, each lasting for the same duration as the original tasks. All project tasks are set to Pending. Actual duration and the actual start and end dates are reset to null values. The state is set to New and percent complete is set to 0. Administrators can override the Script Include CopyProjectFieldOverride to determine which fields are reset or to change the default values.