Create a project task for a waterfall phase.

Before you begin

Role required: it_project_manager

About this task

While creating a project task in the project workbench, the time constraint type is defaulted based on the project type.
  • For a manual project, the default constraint is Start On and cannot be changed.
  • For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required.
  • When the constraint is Start ASAP, the Planned start date is disabled.
  • When you create an agile phase and associate a sprint, the start date of the task is set from the sprint start date and the constraint becomes Start On automatically.

Procedure

  1. Click a waterfall phase in the project workbench timeline.
  2. Click New in the detail view.
  3. Fill out the Project Task form.
  4. Click Submit.