Create tasks from the Project form. The fields appear when the Project Portfolio Management is active and the Project form is in the Basic view. Configure the form to display the fields.

Before you begin

Role required: it_project_manager

Procedure

  1. Navigate to Project > Projects > All.
  2. Select the project from the list.
  3. In the Project Tasks related list, click New.
  4. On the form, fill in the fields.
    Table 2. Details tab
    Field Description
    Milestone Option for converting the task to a milestone.
    Key milestone Option for converting the task to a key milestone.
    Allow dates outside schedule Indicates whether the project task is set to start and end on a non-schedule day (outside regular project schedule) such as on a weekend. An off-schedule task can start any time during the day and on any day of the week.

    For example, if you use the project schedule Monday to Friday, 8:00 to 17:00 and a project task of duration 2 days should start on Saturday, then an off-schedule task is allowed to be scheduled on Saturday and end on Sunday. Similarly, if a task of duration 3 days starts on Friday, then an off-schedule will end on Sunday instead of ending on Tuesday.

    The option is not enabled for a parent task. The value of this field on the parent task is derived from the child tasks.

    Note:
    • There is no difference between an off-schedule and an on-schedule task if there is no schedule defined at the project.
    • 1 day is 8 hours for a task in regular schedule and 24 hours for a task outside schedule.
    Table 4. Notes tab
    Field Description
    Activity / Work notes / Additional comments Information about the milestones, impediments, or changes as the project progresses. Enter notes or comments in the Activity field and click Additional comments or Work notes. The text appears in the feed.
    Table 5. Checklist tab
    Field Description
    Checklist Checklist to track items that must be completed for the task.
  5. Click Submit.

Result

The new task appears in the Project Task related list on the Project form. If time cards are in use, the application creates a time card for the resource.

What to do next

The value in the Percent complete field is related to the State field in the v3 application. If you change the percentage complete from 0 to any other value, the state of the task changes to Work in progress when you save or update the record. Likewise, if you change the state of the task to Closed complete, the Percent complete field is set to 100 and becomes read-only.

If you change the state of a project task from Work in progress to Closed Skipped or Closed Incomplete, the Percent complete field retains the current value and becomes read-only.

The Percent complete field appears in the Gantt chart for parent tasks as a light-colored bar (the part of the task that is complete). The bar overlaps the darker, underlying bar (the full task). For example, a Demo project is 5.41% complete as shown in a pop-up window. The Phase 1 task is about 50% complete (not shown in the pop-up window).

The Project Tasks list and the Project Tasks related list on the Project form include a Dependency field. Any dependencies for a task, such as a parent task, are displayed in this field. Click a dependency record. See Predecessor dependencies in the planning console for a description of what you see in this column.