Create a program to manage projects and demands
- UpdatedJan 30, 2025
- 5 minutes to read
- Yokohama
- IT Program Management
Create a program to manage related projects and demands. Define the duration, estimated cost, benefits, and ROI to the organization.
Before you begin
Role required: it_program_manager
Procedure
- Navigate to All > Project > Programs > Create New.
-
On the Program form, fill in the fields.
Table 1. Program form Field Description Program Name Name of the program. Program manager Program manager assigned to the program. Number System-generated number with a configurable prefix. Portfolio Portfolio to which the program belongs. If you do not select a portfolio for the program, the program becomes a global program. You can associate the projects and demands in a global program with any portfolio.
Priority Priority associated with the program. Status Status of the program. This information rolls up from the status of all the projects that are part of this program. State Current state of the program. Default states: Pending, Open, Work in Progress, Closed Complete, Closed Incomplete, Closed Skipped.
Note: Set the state of the program to Closed manually. The program state does not roll up to a Closed state when program tasks, projects, and demands move to Closed state.Phase Current phase of the program such as Initiating, Planning, and Executing. Business Unit The business unit to which this program belongs. Investment Type Investment type of the program. The default available options are Cost Reduction, End User Experience, Legal and Regulatory, Revenue Generating, Service Sustaining, and Strategic Enabler.
Impacted Business Units Business units of the organization that this program affects. Strategies Strategic objectives of the organization that the program fulfills. A program can fulfill multiple strategic objectives. Note: Leave this field empty if the program does not fulfill any strategic objective.Goals Goals associated to the selected strategy. A program can fulfill multiple goals. If you do not select a strategy, then the Goals list displays all goals in the system.Note: Leave this field empty if there are no goals associated with the program.Description Detailed description of the program. Table 2. Dates section of the Program form Field Description Planned start date Intended program start date. If the start date of associated program tasks, projects, and demands is earlier than the program start date, the start date is adjusted to an earlier date. Removal of a demand or project from the program does not affect the planned start date of the program.
Planned end date Intended program end date. The end date extends based on the end date of the program tasks, projects, and demands. Removal of a demand or project from the program does not impact the planned start date of the program.
You can adjust the program end date manually, based on the start and end date of the associated program tasks, projects, or demands.Note: If a demand with end date later than the program end date is added, the Planned end date field becomes read only.Planned duration Expected duration of this program. The planned duration changes based on the changes in planned start or end date of the program. Actual start date Date on which the program actually starts. Actual end date Date on which the program actually ends. Actual duration Actual duration of the program from program start to program closure. Table 3. Financials section of the Program form Field Description Total planned cost Estimated cost of the program. If there is operational expenditure and capital expenditure associated to the program, then planned cost is sum of operational expenditure and capital expenditure, which is in functional currency.
Planned capital Capital expenditure (Capex) for the program. If there are no cost plans associated to the program, the Capital expense field is editable. Select a currency type and enter a value. Planned operating Operational expenditure (Opex) for the program. If there are no cost plans associated to the program, the Operational expense field is editable. Select a currency type and enter a value. Budget cost Budgeted cost for this program. Actual cost Actual cost of the program. The value rolls up from the cost plan breakdowns from projects and demands in the program.
Planned benefit Planned benefit value for the program. This value rolls up from the benefit plan breakdowns of the program.
You can also enter the value manually. Select a currency from the Currency Type list and enter a value.
Planned returns Planned returns is based on the difference between planned benefit and planned cost. Planned ROI% The result is derived from the values in the Planned return and Planned cost fields. The formula is: planned return / planned cost x 100.
Score The program score is based on the individual scores of the following attributes: risk score, value score, and size score, which in turn are calculated based on risk, planning ROI%, and estimated cost attributes (on a program) respectively. Note: You can configure the formula for score calculation.Risk Risk associated with the program. - Click Submit.
What to do next
Field | Description |
---|---|
PMO Dashboard | Access the PMO dashboard to view comprehensive reports of the projects and demands in the program. |
Program Budget | Allows you to allocate the budget to the program. |
Program Workbench | Access the Program workbench to view details of the projects, demands, and program tasks associated with the program. |
Status Report | View the most recent program status report or create a new program status report. |
Field | Description |
---|---|
Program Tasks | View the list of all associated program tasks. To create a new program task, click the New button. For more information, see Create a program task. |
Projects | View the list of projects included in the program. To create a new project, click New. For more information, see Define a project. To add existing project to the program, click Edit. |
Demands | View the list of demands included in the program. To create a new demand, click New. For more information, see Create a demand. To add existing demand to the program, click Edit. |
Risks | View the list of risks associated with the projects and demands of the program or the program itself. To create a new risk, click New. |
Issues | View the list of issues associated with the projects and demands of the program or the program itself. To create a new issue, click New. |
Cost plans | View the list of all cost plans for projects and demands that are part of the program. |
Benefit Plans | View the list of all benefit plans for projects and demands that are part of the program. |
Program Budget | View the program budget according to fiscal years. Click the amounts in the list to revise them. |
Program Status Reports | View the list of status reports for the program. To generate a new status report, click New. For more information, see Create a program status report. |
Related Content
- Program workbench
The program workbench is a central location for viewing details of a program and the projects and demands that are part of the program.
- Program Dashboard
The PMO dashboard provides a central location to a program manager to generate different graphical reports.