Strategic program planning item form
- UpdatedJan 30, 2025
- 2 minutes to read
- Yokohama
- Strategic Portfolio Management
Learn about the fields of the Strategic program form. Use this form to create or edit the details of a planning item of the type Strategic Program in Strategic Planning.
These fields are displayed on the full details page of the planning item.
Field | Description |
---|---|
Name | Brief description of the planning item. |
Description | Detailed information of the planning item. You can refine strategic program description using the Write planning item skill, if the Now Assist for SPM application is installed. |
State | Current working state of the planning item. |
Initiative | Initiative that this planning item is associated to. |
Owner | User assigned to this planning item. |
Percent complete | Percentage of work completed for this planning item. |
MoSCoW | Priority of this planning item based on its importance. The available options are:
|
Work notes | Notes to capture the updates and discussions on the planning item as the work progresses. |
Field | Description |
---|---|
Approved start date | Approved start date for this planning item. |
Approved end date | Approved end date for this planning item. |
Actual start date | Actual date on which the work for this planning item has started. |
Actual end date | Actual date on which the work for this planning item is complete. |
Priority | Priority of this planning item. |
Business capabilities | Business capabilities of this planning item. |
Business application | Business application that this planning item is related to. |
Other impacted business applications | Business applications that this planning item has an impact on. |
Field | Description |
---|---|
Overview | Business case overview of this planning item. |
Background | Background for this planning item. |
Limitations | Applicable limitations to this planning item. |
Approach | Planned approach to work on this planning item. |
Benefits | Business benefit from this planning item. |
Field | Description |
---|---|
Planned cost | Planned cost to take up this planning item. |
Planned capEx | Planned capital expenditure for this planning item. |
Planned opEx | Planned operational expenditure for this planning item. |
Planned benefit | Planned benefit from this planning item. |
Actual benefit | Actual benefit achieved from this planning item, |
Actual cost | Actual cost on this planning item. |
Actual capEx | Actual value of capital expenditure for this planning item. |
Actual opEx | Actual value of operational expenditure for this planning item. |
Planned ROI | Planned return of investment for this planning item. |
Related Content
- Create planning items from the roadmap view in Strategic Planning Workspace
Create and add new planning items to your portfolio roadmap or free-form roadmap directly from the roadmap view.
- Add planning items to Prioritization page of Strategic Planning Workspace
Add new planning items to your portfolio plan's work backlog in Strategic Planning Workspace and ensure that the work pipeline is current.