If a project or a project task is marked Closed, the project manager can cancel the
associated future resource plans. Similarly, the demand manager can cancel the future
resource plans for a Closed or Deferred demand.
The resource plan to be canceled must be in Confirmed, Planning, or Requested state.
An Allocated resource plan can be canceled if the resource plan start date is later
than the project, task, or demand end date.
Role required: it_project_manager or it_demand_manager
When a project or a project task moves to Closed Complete, Closed Incomplete or
Closed Skipped state, the system prompts a message on the project and project task
forms, and in the planning console for canceling the resource plans if
- there is a corresponding resource plan in Confirmed, Planning, or Requested
state. Or
- there is a resource plan in Allocated state with start date later than the
project or task end date.
A similar message for canceling the resource plans appears on the demand form when a
demand moves to Closed or Deferred state.