You can modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.

Before you begin

Role required: it_project_manager

About this task

Project task dependencies are saved on the Planned Task Relationship [planned_task_rel_planned_task] table. You can access dependencies from the planning console.

Procedure

  1. Double-click a dependency on the Gantt chart of the planning console.
  2. Modify any of the fields (see table).
    Figure 1. Planned Task Relationship form
    Planned Task Relationship form
  3. Click Update.
    You can view dependencies in the Project Task related list on a Project or Project Task form and from the Project Tasks list on the workbench. These columns show the dependencies: