Project Name |
Name of the project. When you create the project from My
Projects Space page, the Project name
field is automatically populated. |
Project manager |
Project manager assigned to the project. |
Status |
Current status of the project. This information is
retrieved from the Overall health
field in the most recent project status report of the
project. |
Number |
System-generated number with a configurable prefix.
|
Percent complete |
Percentage of the project that has been completed.
|
State |
Current state of the project. All new projects begin as
Pending. The state of the project
can be set on the Project form or derived from the task
state. The default available states are: Pending,
Open, Work in Progress, Closed Complete, Closed
Incomplete, and Closed Skipped. You can also
create a custom state for each state type by
overriding the state dictionary attributes. For
example, say for project tasks you have created a custom
state called Testing for the
Work in Progress state type.
When you update the project task state to
Testing, the project state is
also updated to Testing. However,
if you have not created a Testing
state for the Work in Progress
state type, the project state is updated to the default
Work in Progress state.
|
Description |
Detailed description of the project. |
Dates |
Schedule |
Work schedule to be used for this project Note that the
default schedule is an 8-hour work day (from 8 a.m. to 12
p.m. and 1 p.m. to 5 p.m.). A day is considered to be a work
day and not a 24-hour day. |
Planned start date |
Intended date the project begins. This value is set to
the earliest time that the project schedule allows. For
example, if the project task is created at 3 a.m. and
the default schedule is in use (which has an 8 a.m.
start date), then the default task start is 8 a.m. the
next day. Note: The planned start date must be
within 10 years of the current date. The project property
Max date span into future or past from the
current date controls the behavior for
project planned start date. When you create the
project from My Projects Space page, the
Planned start date field is
automatically populated. You must click the calendar
icon and select a date to start the project. Projects do
not automatically start on the planned start
date. |
Planned end date |
Intended date the project ends. After you add tasks, the
value in the field is calculated from the tasks. For a
manual project, any update to the actual start date does
not update the planned end date of the project. Enable
the project property Enable alter of planned
date with Actual for Manual Project to
update the planned end date from the actual start date
and planned duration. |
Planned duration |
Expected duration of this project. After you add tasks,
the value in the field is calculated from the duration of
the tasks. The duration also considers the project schedule,
accounting for any non-work time in the schedule. Note: The
project property
Max duration (in days) allowed for a
project/project task controls the
behavior for project planned duration. For
example, if the default schedule is used, with a
standard 8-hour work day, a project that starts at 8
a.m. on 1 July and ends at noon on 2 July is calculated
as 1 day and 4 hours, not 28 hours. |
Planned effort |
Estimate of time it takes to complete the project. This
calculation sums up planned effort values for all tasks and
stories (in case of Agile and Hybrid projects) in this
project. After you add tasks, this field becomes a
read-only, roll-up calculation and overwrites any earlier
entry that you made. |
Actual start date |
Date on which the project began.
The time component in the actual start and end dates
depends on the value of the Derive time
component from planned dates field in
the Preferences tab when you
manually populate the actual dates.
However, when you change the State
or Percent complete of the
project, the actual dates are auto-populated with the
time component copied from the planned dates. The value
of the Derive time component from planned
dates field has no effect on the time
component of actual dates in this case.
|
Actual end date |
Date on which the project ended. |
Actual duration |
Duration of the project from project start to project
closure. As with the planned duration, the actual duration
shows the total project time and takes the project schedule
into consideration. |
Actual effort |
Actual number of hours charged to the resources on this
project. If you are using the Time Cards application, it
automatically calculates the value for this field. It uses
the totals for the time worked from the approved time cards
of all the resources who worked on a project and all its
tasks. Note: The actual effort from the stories for Agile
and Hybrid projects is also rolled up to the project's
actual effort. The field is not editable if the
Update actual effort from time
card field is set to Yes in the
Preferences tab. |
Details |
Portfolio |
Primary portfolio to which the project belongs. A project
can belong to multiple portfolios. Note:
- If a project, for which the
Portfolio field is not set
is associated to a portfolio using the portfolio
form, then the portfolio name is populated in the
Portfolio field.
- If a portfolio is deleted, the portfolio name is
removed from the Portfolio
field on the Project form.
|
Program |
Program to which the project belongs. Note: If the
Portfolio field is not set,
you can select from the list of all programs in the
system. If the Portfolio field is
set, you cannot select programs that belong to other
portfolios. |
Investment Class |
Type of investment class category assigned to the
project:
- Run: Investment made to
sustain the existing business.
- Change: Investment made to
implement a change in business.
|
Investment Type |
Investment type of the project. The default available
options are Cost Reduction, End User Experience, Legal
and Regulatory, Revenue Generating, Service Sustaining,
and Strategic Enabler. |
Execution Type |
Execution methodology used to run the project:
Waterfall,
Agile, and
Hybrid. The default value is
Waterfall. The
Execution Type field
selection determines the related links and related lists
that are available. For example, the Agile
Planning & Tracking related link
appears when you set the Execution Type value to
Agile. You must have the
appropriate plugins such as Agile Development 2.0 and Test Management to view these related links and related lists. Also,
you must have the appropriate role to use these related
links and related lists. |
Demand |
Demand from which the project was created. The field is
visible only if the project has a demand associated to
it. |
Phase |
Current phase of the project. In addition to the
Phase field, the different
project phases are also shown at the top of each project
record. The selected phase is highlighted. The
default phases are Initiating,
Planning,
Executing,
Delivering, and
Closing. |
Department |
Department in a business unit to which the project
belongs. |
Business Unit |
Business unit to which the project belongs. |
Impacted Business Units |
Business unit that is impacted by the project. |
Business Capabilities |
If the project is to change, enhance, or add one or more
business capabilities, those capabilities can be associated
with the project. Business capabilities are defined in the
Application Portfolio Management module. |
Business Applications |
If the project is to change, enhance, or add one or more
business applications, those applications can be associated
with the project. Business applications are defined in the
Application Portfolio Management module. You can select
any business application in your enterprise regardless
of whether it is related to the capability selected in
the Business Capabilities
field. |
Business
Case |
Note: When a demand gets converted into a project, the data
in Business Case tab gets carried
forward from demand to project.
|
Strategies |
Strategic objectives of the organization that the project
fulfills. A project can fulfill multiple strategic
objectives. If a Business Unit
for the project is selected in
Details tab, then the choice
list displays the business strategies for the selected
business unit along with other enterprise
strategies. |
Goals |
Goals associated with the selected strategy. A project
can fulfill multiple goals. If a strategy is not selected,
then all goals are displayed in the choice
list. |
Business case |
Business arguments that support the project. |
Risk of performing |
Risks associated if the project is carried out. |
Risk of not performing |
Risks associated if the project is not carried out, for
example, risk of loss of opportunity. |
Enablers |
Key enablers for the project. |
Barriers |
Major barriers to the project. |
In scope |
Scope of the project. The scope is the set of boundaries
that define the extent of a project. |
Out of scope |
Activities or deliverables that are not in the scope of
the project. Anything that is not specifically defined in
the scope is out of scope. |
Assumptions |
Assumptions made for the project. Assumptions help define
scope and risks, and fine-tune the estimates for time and
cost. |
Financials |
Rate Model |
Rate model assigned to the project. The rate model is used to derive hourly rates
for the associated resource plans and time cards.
When you create a project from a demand, the rate model
is copied from the demand to the project.
The subprojects in a project derive their resource plan
calculations from the rate model associated with the top
task.
If the assigned rate model is removed or replaced or the
hourly rates in the rate model are changed, the cost
fields on the associated resource plans are not
recalculated automatically. You must update costs of all resource plans in the
project using the Recalculate
Resource Costs menu option to reflect
new rates from the rate model.
You can also update costs of a single resource plan one at a
time.
|
Total planned cost |
Estimated cost of the project. If an operational
expenditure, capital expenditure, or both are associated
with the project, then the planned cost is the sum of
the operational expenditure and capital expenditure,
which is in the selected currency for the
project. For Agile and Hybrid projects, the
planned cost for stories is considered when the resource
plan is created for Agile assignment group. Note: To
create a resource plan for Agile assignment group, you
must assign the pps_resource role to the
group. |
Planned capital |
Capital expenditure (Capex) for the project. If no cost
plans are associated with the project, the
Planned capital field is
editable. Select a currency type and enter a value. |
Planned operating |
Operational expenditure (Opex) for the project. If no
cost plans are associated with the project, the
Planned operating field is
editable. Select a currency type and enter a value. |
Budget cost |
Budgeted cost for this project. This field is
automatically populated from the project budget breakdowns
in the cost plan breakdown table. When project funds are
allocated for a fiscal year, the cost plan breakdown stores
the budget allocation for each fiscal period. These amounts
are rolled up and stored in the budget cost. To manually
enter a value, select a currency icon and enter the
value. |
Actual cost |
Actual cost of this project. Select a currency icon and
enter a value. |
Estimate at completion |
Sum of all actuals for past fiscal periods added to the
planned cost for future fiscal periods. Note: The current
month is considered as a future month for EAC
calculation purposes. For example, if the
duration of a project is from January 01 to December 31
and you check the Estimate at Completion in the month of
May, it is calculated as: Sum of actuals from
Jan to April + Sum of planned cost from May to
December . |
Planned benefit |
Planned benefit for the project. This value is rolled
up from the benefit breakdown of the project. You
can also enter the value manually. Select a currency
icon and enter a value. |
Planned return |
The Planned returns value is
derived from the difference between the Planned
benefit and Planned
cost values: (The value in the
Planned benefit field – the
value in the Planned cost
field) |
Planned ROI% |
The ROI (return on investment) percentage result is
calculated based on values in the Planned
return and Estimated
cost fields. (Planned
return/Estimated cost x 100)
|
Discount Rate % |
Project discount rate. The discount rate is the
interest rate to determine the present value of future
cash flows. |
Net present value |
Present value of future cash based on the given annual
interest rate. This value is a measure for comparing money
spent today against future expected financial benefits.
This information is useful when evaluating the overall
investment performance. For example, at 12%
discount rate, $1.00 today is worth $0.80 in two years.
Therefore, expecting to receive $1.00 in two years is
same as receiving $0.80 today. Net present value
(NPV) is calculated from the estimated cost per year,
the planned benefit per year, and the discount rate for
the project. |
Internal rate of return % |
Annual interest rate required to achieve an NPV of
zero. Internal rate of return (IRR) helps to determine
which projects can deliver higher rate of return in
terms of revenue. |
Estimate to completion |
Sum of all planned costs for future fiscal
periods. Note: The current month is considered as a
future month for ETC calculation
purposes. |
Score |
Risk Score |
Calculated based on the project risk. |
Value Score |
Calculated based on the ROI% of the project. |
Size Score |
Calculated based on the value in the Planned
Cost field. |
Score |
Calculated based on the individual scores of the
attributes Risk Score,
Value Score, and Size
Score, which in turn are calculated based on
the risk, planning ROI%, and estimated cost attributes on a
project, respectively. Note:
- You can configure the formula for score
calculation.
- When a demand is converted to a project, the
score calculated on the demand is carried forward
to the project.
|
Notes |
Watch list |
Users who have subscribed to project notifications.
|
Work notes list |
Users who have chosen to receive email notifications when
the work notes on the project are updated. |
Activity / Work notes |
Information about the milestones, impediments, or changes
as the project progresses. Enter the notes in the
Activity field and click
Work notes. The text appears in
the feed. |
Preferences |
Allow time card reporting on |
Level at which the time
cards for project tasks
can be created:
- Project only: All time cards
for the project are created at the project level
only. For example, if a user is assigned to multiple
tasks in a project, then the time spent on all tasks
is recorded under one time card only for the
project.
Note: In the Time Sheet Portal,
tasks of the project are listed in the
Tasks tab. For these tasks,
the Add to Time Sheet and
Add selected to Time Sheet
options are not available. Only the
Quick Add option is
available. On clicking Quick
Add, a time card is created against
the top project, not against the task.
- Project tasks only: Separate
time cards are created corresponding to each planned
task.
Note: In the Time Sheet Portal, the
Add to Time Sheet,
Quick Add, and
Add selected to Time Sheet
options are not available for the project.
- Project and project tasks:
Time cards can be created at the project as well as
the project task level. This is the default set
value.
- No time reporting: No time
cards are created for the project. If the user
submits the time card manually, the business rules
prevent the user from submitting the time
card.
Note: In the Time Sheet Portal, the
Add to Time Sheet,
Quick Add, and
Add selected to Time Sheet
options are not available for both project and
project tasks.
|
Update actual effort from time card |
Determines whether the Actual
effort field on the
Dates tab should be updated based
on the hours entered in the time cards for the project.
If the field is set to Yes, then the
Actual effort field is not
editable. If it is set to No, then the actual hours from
time cards are not rolled up to the project and task. By
default, it is set to No. |
Calculation |
Type of calculation to use for task dependencies:
-
Manual: Task dates do not
reflect any changes made to dependencies.
-
Automatic: Task dates are
automatically updated to reflect any changes made to
dependent or child tasks.
|
Show on Program Status Report |
Option to specify whether the project and it's key
aspects such as cost, resource, scope, and schedule should
be included in the status report of the program to which the
project belongs. Default: Selected |
Derive assignee list from resource plan |
Option to constrain the resources in the
Assigned to and
Additional assignee list fields
on the project and project task forms to be derived only
from the associated allocated resource plans. |
Recalculate score on project change |
Determines whether to recalculate and update the project
score.
- If the value of the field is set to Yes, project
score is recalculated when the projects planned
ROI%, estimated cost, or risk is modified.
- If the value of the field is set to No, the project
score remains the same even if the project's planned
ROI%, estimated cost, or risk is modified. The value
of the field can be set to No when the user wants to
preserve the score value while converting the
project to a demand.
|
Project schedule date format |
Determines whether the dates in the planning console
should be displayed with the time component. |
Derive time component from planned dates |
Determines whether the time component in the actual start
and end dates should be copied from the time component in
the planned start and end dates. By default, it is set to
false. If the Project schedule date
format field is set to
Date, this field is
auto-checked and disabled. Note: When you change the
State or Percent
complete value for the project, the
actual dates are auto-populated with the time component
copied from the planned dates. The value of the
Derive time component from planned
dates field has no effect on the time
component of the actual dates in this case. The value of
the field affects the time component only when you
populate the actual dates manually. |
Risk
Overview |
Note: This tab appears only when you have the Advanced Risk
plugin activated and the Enable Advanced Risk
PPM Integration property under is enabled.
|
Inherent risk |
Score of inherent risk automatically calculated from risk
assessment. |
Residual risk |
Score of residual risk automatically calculated from risk
assessment. |
Inherent Heatmap |
Heatmap of the inherent risks. |
Residual Heatmap |
Heatmap of the residual risks. |