Add an external dependency between two projects on the planning
console.
Use the work breakdown structure (WBS) column
of the planning
console to create a dependency between
the
different projects
tasks.
Role required: it_project_manager
-
Right-click a task in the WBS
column of the planning console.
-
Click Add External Dependency.
-
On the form, fill in the fields.
Table 1. Add Dependency form
Field |
Description |
Project |
The predecessor project
that the dependency is
added
from. |
Task |
The task in the predecessor project
that the dependency is
added
from. |
Dependency Type |
The type of external dependency:
Hard
or
Soft. |
-
Click OK.
Note: The external dependencies are displayed only when the
Hide External
Dependencies switch on
the
planning console is turned off. However, the
Dependency column in
the
WBS section of the successor project still shows the value of
the
external dependency.
In the example below, an external dependency is created between two projects P1 and
P2. P1T1 is a shadow task of predecessor project P1, and PRJ0010127\1fs+0 is the
external dependency value in
the
Dependency column of the planning console of
the
successor project P2.

Check for any external dependency related notifications that may impact the project or its tasks.