Add an external dependency on planning console
-
- UpdatedJan 30, 2025
- 2 minutes to read
- Yokohama
- Project Portfolio Management
Add an external dependency between two projects on the planning console. Use the work breakdown structure (WBS) column of the planning console to create a dependency between the different projects tasks.
Before you begin
Role required: it_project_manager
Procedure
Result
- A shadow task corresponding to the predecessor task appears in the WBS section
of the planning console of the successor project. A similar shadow task
corresponding to the successor task appears in the WBS section of the planning
console of the predecessor project.
A shadow task is shown as a grayed out task in WBS column.
- A shadow task corresponding to the predecessor task appears in the Project Tasks related list on the successor project form. A similar shadow task for the successor task appears in the Project Tasks related list on the predecessor project form.
- The Dependency column in WBS column of the planning
console of the successor project shows the external dependency value between the
projects and tasks. The external dependency value has the following
format:
{project_number}\{WBS_number}{dependency_type}+{lag_time}
Whereproject_number
is the number of the predecessor project.WBS_number
is the number of the predecessor task in the relationship.dependency_type
is the finish to start dependency type that the application supports.lag_time
is the amount of time, in days, to delay the start of the dependent task. This value can be positive or negative integers.
Example
What to do next
Check for any external dependency related notifications that may impact the project or its tasks.
Related Content
- Types of external dependencies
The Project management application supports two types of external dependencies - hard and soft.