Export project tasks

Log in to subscribe to topics and get notified when content changes.

Export project tasks

The task being exported must be associated with a project that uses either the Project Management Schedule or the Default MS Project schedule.

Before you begin

Role required: it_project_manager

Procedure

  1. Navigate to Project > Projects > All.
  2. Open the project.
  3. Scroll to the Project Tasks related list and click a task number to open the Project Task form.
  4. Right-click the form header and select Export Task to MS Project from the context menu.

    The task is exported to a folder on your system.

  5. Open Microsoft Project to import the exported project task files. Refer to Microsoft product documentation for instructions.