During calculation of project schedule in the planning console, it is possible to build your project structure quickly on the client side (browser) without having to save details in the server for each interaction. It prevents any time lags that occur after you perform any actions in the planning console, and improves the scheduling performance.

For example, when a project manager changes dates on a project task in the planning console, re-calculating the dates for the dependent tasks and the project can cause time lag if each interaction is saved to the server. Similarly, when a new task or a dependency is created, there can be a time lag before the new dates are displayed if they are saved on the server side each time.

When client side planning is enabled, the changes such as re-calculation of dates are not posted to the server immediately. All the changes in planning console are kept on client side until the user explicitly saves the changes to be committed to the server.

Exceptions

There are a few actions for which you must save your changes immediately to the server side before proceeding such as:
  • Create baseline
  • Copy project
  • Copy partial project
  • Add child tasks
  • Add external dependency
  • Edit Assigned to
  • Edit Additional Assignees

In addition, if you enable custom business rules on any of the columns, those columns are also part of exceptions.