Measure time and effort

Measure time and effort

The Planned Task [planned_task] table provides standard fields for tracking duration and effort.

Duration measures time from start to end date. Effort measures hours of work exerted on the project.

Duration
  • Planned duration: The projected length of time for the planned task.
  • Actual duration: The actual length of time so far for the planned task.
  • Remaining duration: The Planned duration minus the Actual duration, which represents the projected length of time left.
Effort
  • Planned effort: The projected amount of time that will be spent on the planned task.
  • Actual effort: The actual amount of time that has already been spent on the planned task.
  • Remaining effort: The Planned effort minus the Actual effort, which represents the project amount of work left.
  • Percent complete: The Actual effort divided by the Planned effort, which estimates the percentage of planned work which has been completed.