Execution plan tasks

An execution plan contains one or more execution plan tasks, such as for obtaining approval. Execution plan tasks are assigned to a fulfillment group.

Each task represents work to be completed by a specific group as part of the overall request fulfillment process.

Administrators create templates for tasks as part of defining an execution plan. The catalog tasks themselves are then created when the relevant item is requested, based on these task templates.

Set up and execution plan approval task

Approval tasks are specific types of tasks within execution plans.

About this task

If an approval task is rejected, the execution plan can roll back to a previous task.

To set up an approval task including a rollback action:


  1. Navigate to Service Catalog > Execution Plans.
  2. Select an execution plan.
  3. From the Execution Plan Tasks related list, select New Approval to create the approval task.
  4. Fill in the fields for that approval task.
    Figure 1. Upon Reject
  5. Use the Upon reject field to define the action to take if the task is rejected:
    • Cancel all future Tasks: [default] cancels all future tasks in the execution plan and also cancels the parent request item.
    • Go to a previous Task: displays the Rejection goto field where you can select which task this execution plan rolls back to.
  6. Save the task, then scroll down to the Approved By list and select one or more approvers for the tasks.

    You can also use an Approval script to select approvers.

  7. Select Update to add the task to the execution plan.

    This example shows how the process works in practice, using a request to order a Blackberry phone.

    First, the request is ordered:
    Figure 2. Rollback 1
    Next, complete the first two steps, which leads to the approval task.
    Figure 3. Rollback 2
    Reject the request to roll back the execution plan to a previous task, and reset any intermediate tasks to pending:
    Figure 4. Rollback 3
    After a plan has been rolled back, ServiceNow adds to the rolled-back task a note indicating that it was rolled back and why.
    Note: Rolling back reverts all intermediate tasks within the execution plan. Other plans within the same request are not rolled back, however.

Set up a fulfillment group

Fulfillment groups perform the tasks related to fulfilling an order.

About this task

This group setting can include approving an order based on characteristics such as content and price, or any direct action required to complete the order. For example, loading software or installing hardware. Any existing user group (in User Administration > Groups) can be assigned fulfillment tasks.

To create a group specifically for order fulfillment:


  1. Navigate to Service Catalog > Catalog Policy > Fulfillment Groups.
  2. Click New.
  3. Fill in the Group form as described under creating groups.
    These groups have the type catalog and are assigned the catalog and itil roles, but are otherwise normal groups.

Delivery information for tasks

When managing execution plans, catalog administrators can specify the delivery information to provide an estimated date of delivery based on the execution plan.

Use the Total delivery time field to specify an estimated delivery time for each task in your execution plan. This estimate is calculated based on the combined total of times for the tasks in that execution plan.

By default, time estimates do not use a "working days" calendar system, but are based on simple elapsed time. For example, for a 5-day execution plan, if you submit the request on a Friday, the delivery date is Wednesday of the following week. This estimate means five elapsed days later, even if your organization does not work on weekends.

Use the On Calendar field to specify a calendar system to apply to the execution plan, to help estimate more accurate delivery times.

If using this calendar system for estimated delivery time, ensure that estimates are expressed in working hours and days. For example, a task which is supposed to take one day on a 9-5 calendar is assumed to take 24 working hours. This process takes three working days.
Note: This calendar system is used to help provide delivery estimates only, and is not linked to any SLAs you have set on execution tasks.

Skipped tasks

If a task is skipped, the request fulfillment process moves on to the next task.

If the last task in an execution plan is skipped, the process is finished and the appropriate request item is closed as complete. Skipped tasks have their state set to Closed Skipped and display as gray boxes on a requested items list.
Figure 5. Processing Skipped Tasks