Contents IT Business Management Previous Topic Next Topic Create a milestone Subscribe Log in to subscribe to topics and get notified when content changes. ... SAVE AS PDF Selected Topic Topic & Subtopics All Topics in Contents Share Create a milestone A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones. Before you beginRole required: it_project_manager About this task Note: Milestones cannot be shared between projects unless one project is nested under another project. Procedure Create a project task and give the Duration field a value of 0. Open the planning console Gantt chart and verify that it appears as a diamond. You can also convert a task to milestone through planning console. Result Related TasksCreate a project taskAccept or reject project task notificationsRelated ConceptsProject task relationships and dependenciesChange requests and project tasksProject task checklistsTask resources On this page Send Feedback Previous Topic Next Topic
Create a milestone A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones. Before you beginRole required: it_project_manager About this task Note: Milestones cannot be shared between projects unless one project is nested under another project. Procedure Create a project task and give the Duration field a value of 0. Open the planning console Gantt chart and verify that it appears as a diamond. You can also convert a task to milestone through planning console. Result Related TasksCreate a project taskAccept or reject project task notificationsRelated ConceptsProject task relationships and dependenciesChange requests and project tasksProject task checklistsTask resources
Create a milestone A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones. Before you beginRole required: it_project_manager About this task Note: Milestones cannot be shared between projects unless one project is nested under another project. Procedure Create a project task and give the Duration field a value of 0. Open the planning console Gantt chart and verify that it appears as a diamond. You can also convert a task to milestone through planning console. Result Related TasksCreate a project taskAccept or reject project task notificationsRelated ConceptsProject task relationships and dependenciesChange requests and project tasksProject task checklistsTask resources