Project and project task states

Project and project task states

In the base system, the states in project and project task inherit the states in Task table.

The states are grouped into different categories as shown below:
State Label Category
-5 Pending Pending
1 Open Open
2 Work in Progress Work in Progress
3 Closed Complete Closed
4 Closed Incomplete Closed
7 Closed Skipped Closed

The category information for the states is declared in dictionary override of State column in Planned task (planned_task) table in Attributes field. Planned task is the parent table for project and project task tables.