Work order task start and end dates

Dynamic scheduling uses work order task Window start and Window end dates to schedule tasks.

If both the Window start and Window end dates are present in the work order tasks, dynamic scheduling uses these dates.

If the task has a Window start date but the date has passed, dynamic scheduling uses the current date and time for this value.

If the task has a Window start date but no Window end date, dynamic scheduling uses the com.snc.wm.wo.task_window_day property to determine this value.

If the task has no Window start date but has a Window end date, dynamic scheduling uses the current time for this value.

If the task has neither a Window start nor a Window end date, dynamic scheduling uses the current time and date for the Window start and the com.snc.wm.wo.task_window_day property for the Window end.