Create multiple sprints

To save time, you can create multiple sprints at one time.

About this task

If the sprint start and end dates are outside the release start and end dates, the application prompts you to change the release start and end dates appropriately.

Procedure

  1. Navigate to Agile Development > Planning > Open Releases.
  2. Select an open release.
  3. Right-click the header bar and select Add Sprints.
  4. Fill in the information.

    The example shows Team A starting 6 sprints of 14 days each beginning October 1, 2012.

  5. Click OK.