Assign a project schedule

Assign a project schedule

Without an assigned schedule, a project calculates a day as a full 24 work hours. To schedule tasks by a more realistic work day, assign a schedule to the project. If the schedules provided in the base system do not suit your needs, define a new one.

Before you begin

Role required: it_project_manager

Procedure

  1. Open a project.
  2. If the Default view is active, right-click the header bar and select View > Advanced.
  3. Select a schedule in the Schedule field.