Set a downstream task

Setting a work order task as a downstream task means that this task cannot be started until any upstream tasks have been completed.

Before you begin

Role required: wm_qualifier or qualifier combination role

Procedure

  1. Navigate to a work order.
  2. Open a work order task in the Draft state.
  3. In the Dependents related list, click New.
  4. Select a Downstream task.
    Only tasks for the same work order are listed.
  5. Click Submit.