Remove a dependency

Use the planning console to remove a dependency that is no longer necessary.

About this task

Removing the dependency also deletes the dependency record in the Planned Task Relationship table.

Procedure

  1. Open the project in the planning console.
  2. Do either of the following:
    OptionDescription
    On the Gantt chart Double-click the relationship and click Delete on the Planned Task Relationship form that appears.
    On the WBS list Delete the value in the Predecessor column.